Project Description: Stormwater improvements to increase system capacity and provide a higher level of protection. Project includes 8 phases.
Project Budget: $1.25 million
Additional Details:
Phases 1 and 2 - Construction complete; $350,000 expended.
Phase 3 - Survey complete; 50% design underway; anticipate construction start Winter 2023.
Phase 4 - Survey complete; 50% design underway; anticipate construction start Spring 2024.