Project Description: Several drainage outfalls are in need of major maintenance work such as sediment removal and/or slope stabilization work.
Project Budget: $5,384,332
Additional Information:
1. Camelot Drainage Improvements Phase 2 - Survey complete; wetland delineation and 50% design) in-house) underway; anticipates construction start late Fall 2023
2. Haledon Dr. Drainage Improvements - On hold pending completion of Crestwood 2&3 MDP
3. Hazel Ct. Drainage Improvements - Preliminary design and survey underway
4. Wesley Rd. Drainage Improvements - Preliminary design and survey underway