Property Acquisition
This program will address existing deficiencies along the City's rural roads. The first project in this program will add three feet of pavement widening, 15 feet of unpaved shoulder widening, and an improved ditch to four-foot bottom with 2-to-1 side slopes on Shillelagh Road from Herring Ditch to 3,600 feet north of the ditch. Awaiting utility relocation and completion of right-of-way acquisition.
Project Design Start: Fall 2017
Design Completion: Spring 2021
Construction Start: April 2023
Construction Completion: October 2023
Project Budget: $3.05 million