Procurement
This VDOT-funded project includes paving of the existing parking area adjacent to the boat ramp, construction of a rest area facility, and associated improvements at the Ballahack Boat Ramp area of the Great Dismal Swamp. Public Works is coordinating funding availability with Parks, Recreation and Tourism. Project has been awarded and anticipate construction to start in June 2023.
Project Design Start: August 2017
Design Completion: August 2020
Project Construction Start: June 2023
Project Budget: $401,791