Washington Drive
Drainage Improvements
Unicorn Trail to E Street
Public Works Project Spotlight
Washington Drive Drainage
Project Overview:
Roadside drainage improvements will be provided from 300’ east of E Street to 300’ west of Unicorn Trail. The work along this portion of Washington Drive will be performed within the existing 50’ right-of-way. The following improvements will be made to the area:
- The ditches adjacent to the pavement will be filled, providing a four foot to ;five foot roadside shoulder.
- New ditches will be graded from the new shoulder to the right-of-way line.
- The north side will drain to several cross pipes connecting to the drainage trunk line along the south side.
- Disturbed concrete and asphalt entrances will be replaced with concrete entrances.
- Most of the trees and shrubs within the right-of-way will be removed.
- The proposed 36” outfall pipe will follow the Dominion Virginia Power right-of-way and spill into Herring Ditch, 700’ west of Washington Drive.
The project was awarded to Rountree Construction Company, Inc. in the amount of $634,862 on May 22, 2009. Construction near Herring Ditch began in October 2009.
Project Timeline:
Award: May 22, 2009
Notice to Proceed: Mid June 2009
Final Completion: July 30, 2010