Home Contact FAQs A-Z Index Site Map Search

Public Works Project Spotlight - Long Bridge Replacement

Project Updates

Project Update

07/08/10

This month activity will include pouring the approach slabs and bridge deck.

If you have a comment or question, we would like to hear from you.

Project Update

06/07/10

The project is moving along on schedule and will be completed in August.

If you have a comment or question, we would like to hear from you.

Project Update

04/13/10

From Kristina Davis, Project Engineer:

"Over the next week citizens will see our crews begin driving piles for the east portion of the new bridge, in addition to continuing demolition of the old bridge."

If you have a comment or question, we would like to hear from you.

Project Update

02/16/10

Crews are currently working on installing the new 12" waterline attached to the bridge.

We anticipate having traffic moving to the east side in early March.

If you have a comment or question, we would like to hear from you.

Project Update

09/28/09

The steel attached to the crane is the pile driving hammer, used to drive the piles. The rods in the water are a pile driving template. It is a frame used to line up the pile while it is being driven. - photo
The steel attached to the crane is the pile driving hammer, used to drive the piles. The rods in the water are a pile driving template. It is a frame used to line up the pile while it is being driven.

The steel attached to the crane is the pile driving hammer, used to drive the piles. The rods in the water are a pile driving template. It is a frame used to line up the pile while it is being driven. - photo
The steel attached to the crane is the pile driving hammer, used to drive the piles. The rods in the water are a pile driving template. It is a frame used to line up the pile while it is being driven.

 

To comply with environmental standards, a turbidity curtain, used for erosion and sediment control, is placed in the water. - photo
To comply with environmental standards, a turbidity curtain, used for erosion and sediment control, is placed in the water.

 

If you have a comment or question, we would like to hear from you.

Project Update

08/10/09

From Project Manager Kevin M. Lundgren, P.E.:

"All utilities have been relocated underground to be clear of construction. The contractor is now working on widening the pavement on the east side. This should take approximately one week. At that point they will begin demolishing the bridge on the opposite side."

If you have a comment or question, we would like to hear from you.

Project Update

06/17/09

Click thumbnails for videos.

 

 

If you have a comment or question, we would like to hear from you.