ACTIVE
Stormwater & Drainage Projects

Below is a listing along with maps that describe active stormwater & drainage projects.

Please note: Budget includes design, property acquisition for right of way and easements, and construction costs

Last update: August, 2009 (Projects are updated quarterly.)

graphic - map of Chesapeake

PRINTABLE MAP
Active Stormwater & Drainage Projects map
Adobe pdf iconpdf (2.6 MB)

 

Stormwater & Drainage Improvement Areas

 

ACTIVE PROJECTS

    CAMELOT DRAINAGE PHASE II

    Provide new drainage pipe outfall for the Camelot subdivision lake system. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $1,520,000
    Funding Source: Capital Improvement Budget FY07 to FY09
    Construction Start Date:: TBD Completion Date: TBD

    CAMPOSTELLA/WAKE AVE. DRAINAGE IMPROVEMENTS

    Provide new Quad Box Culvert crossing under Campostella Road near Wake Ave. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $1,200,000
    Funding Source: Storm Water Fee – CIB FY07 to FY08
    Construction Start Date: TBD Completion Date: TBD

    CAMPOSTELLA ROAD DRAINAGE IMPROVEMENTS PHASE 1

    Provide ditch improvements from Campostella Road Military Highway. If funding from Campostella / Wake Ave and Phase I allow, phase II provides a new culvert crossing under Military Highway Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $87,500
    Funding Source: Storm Water Fee – CIB FY07 to FY08
    Construction Start Date: TBD Completion Date: TBD

    CREST HARBOR DRAINAGE IMPROVEMENTS

    Replace storm water pipe on Mains Creek Rd. Replace pipe at outfalls and provide tide flex valves on outfall pipes. Regrade ditch along Mullen Rd. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $500,000
    Funding Source: City Capital Improvement Budget – FY07 to FY09
    Construction Start Date: 09/09 Completion Date: 04/10

    DELIA DRIVE DRAINAGE OUTFALL IMPROVEMENTS

    Reroute drainage from Expressway SWM Basin to new outfall. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $355,000
    Funding Source: Council Appropriation – April 10, 2007
    Construction Start Date: TBD Completion Date: TBD

    DUNEDIN AREA DRAINAGE IMPROVEMENTS

    Provide drainage from undeveloped area adjacent to Dunedin subdivision to existing storm water system. Construction schedule will be established when design is complete.

    Project Managed By: City Status: In Design Budget: $250,000
    Funding Source: City Capital Improvement Budget FY08 to FY09
    Construction Start Date: TBD Completion Date: TBD

    FENTRESS OUTFALL

    Improve 2,700 feet of drainage ditch from Mount Pleasant Rd through Back Road.

    Project Managed By: City Status: In Design Budget: $272,630
    Funding Source: Developer Pro Rata Drainage Funds
    Construction Start Date: 10/09 Completion Date: 04/10

    HALIFAX ST OUTFALL IMPROVEMENTS

    The project includes the removal of existing pipe system and the installation of a larger pipe system to handle the stormwater runoff from several areas within Chesapeake and City of Norfolk. Construction schedule will be established when design is completed.
    Project Managed By: City Status: Study Budget: $1,000,000
    Funding Source: City Capital Improvement Budget FY09
    Construction Start Date: TBD Completion Date: TBD

    LOXLEY GARDENS DRAINAGE IMPROVEMENTS

    Provide drainage improvements to relieve ponding at three residential intersections and improve 2,300 feet of outfall channel from Loxley Gardens through Gilmerton Rd.

    Project Managed By: City Status: In Design Budget: $450,000
    Funding Source: City Capital Improvement Budget FY08
    Construction Start Date: 02/10 Completion Date: 08/10

    MONEY POINT STORMWATER IMPROVEMENTS Phase II

    Improve outfall and storm water system in Money Point including BMP installation. Construction scheduled will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $455,667
    Funding Source: City Funds and State/Federal Matching Funds Grant
    Construction Start Date: TBD Completion Date: TBD

    MURRAY DR/GREENHAVEN AREA OUTFALL IMPROVEMENTS

    Improve outfall ditch and install larger culverts. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $3,500,000
    Funding Source: City Capital Improvement Budget FY09 and FY10
    Construction Start Date: TBD Completion Date: TBD

    PARTRIDGE/CLOVERDALE AREA DRAINAGE IMPROVEMENTS

    Improve drainage by installing valley gutter/edging and pipe system. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $600,000
    Funding Source: City Capital Improvement Budget FY08
    Construction Start Date: TBD Completion Date: TBD

    POINDEXTER ST OUTFALL IMPROVEMENTS

    Improve the stormwater system for the Poindexter corridor from Bainbridge to the outfall by replacing existing outfall and constructing a BMP.

    Project Managed By: City Status: Construction Budget: $400,000
    Funding Source: City Appropriations – March 2008
    Construction Start Date: 04/09 Completion Date: 09/09

    SCENIC BLVD DRAINAGE IMPROVEMENTS

    Regrade ditch along Scenic Blvd from Denver St to Washington Dr and reset driveway pipes. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $260,000
    Funding Source: City Capital Improvement Budget FY09
    Construction Start Date: TBD Completion Date: TBD

    SHILLELAGH ROADSIDE DITCH RELOCATION

    Regrade 2000 feet of ditch and reset driveway pipes. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $600,000
    Funding Source: City Capital Improvement Budget FY08
    Construction Start Date: TBD Completion Date: TBD

    SUNRAY DRAINAGE OUTFALL – PHASE III

    Provide drainage crossing improvements under Norfolk and Southern Railroad tracks.

    Project Managed By: City Status: In Design Budget: $679,557
    Funding Source: City Capital Improvement Budget FY04
    Construction Start Date: TBD Completion Date: TBD

    TRIPLE DECKER OVERPASS FORCEMAIN

    Replace the existing 12" outfall force main. Railroad permit required. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $89,340
    Funding Source: City Operating Budget
    Construction Start Date: TBD Completion Date: TBD

    WASHINGTON DRIVE DRAINAGE IMPROVEMENTS

    Regrade ditch along both sides of Washington Drive from E Street to Unicorn Drive and reset driveway pipes.

    Project Managed By: City Status: In Design Budget: $560,000
    Funding Source: City Capital Improvement Budget FY08
    Construction Start Date: 08/09 Completion Date: 03/10

    WATERS ROAD DITCH AND SHOULDER IMPROVEMENTS

    Install to new pipe and provide shoulder to the west side of Waters Road from Washington Drive to Chattanooga Street. Construction schedule will be established when design is completed.

    Project Managed By: Consultant Status: In Design Budget: $3,042,000
    Funding Source: Council Appropriation – February, 2008
    Construction Start Date: TBD Completion Date: TBD

    WILLOW LAKE/LAKE SHORE CULVERT REPLACEMENT

    Install larger culverts to improve storm water drainage. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $700,000
    Funding Source: Council Appropriation – April 10, 2007
    Construction Start Date: TBD Completion Date: TBD

    YADKIN ROAD OUTFALL IMPROVEMENT

    Replace existing culvert under Norfolk and Southern Railroad near Yadkin Road, add a detention pond/BMP and improve outfall. Construction schedule will be established when design is completed.

    Project Managed By: City Status: In Design Budget: $550,000
    Funding Source: Council Appropriation – April 10, 2007
    Construction Start Date: TBD Completion Date: TBD

RECENTLY COMPLETED PROJECTS

    FERNWOOD FARMS DRAINAGE IMPROVEMENTS

    Regrade ditches along and Maple Shore Dr and Fernwood Farms Rd.

    Project Managed By: City Status: Completed Budget: $250,000
    Funding Source: City Appropriation – March 2008
    Construction Start Date: 03/09  Completion Date: 06/09 

    MONEY POINT STORMWATER IMPROVEMENTS Phase I

    Improve outfall and storm water system in Money Point including BMP installation.

    Project Managed By: City Status: Completed Budget: $455,667 
    Funding Source: City Funds and State/Federal Matching Funds Grant
    Construction Start Date: 03/09 Completion Date: 06/09