Long Bridge Replacement
Scope of the project:
- The project includes construction of a 4-lane wide, 3 span pre-stressed concrete slab replacement bridge, widening and reconstruction of approximately 881 lineal feet of approach roadway; associated water main and drainage adjustments; and demolition of existing bridge. The project will be constructed in stages to maintain 2-way traffic on the highway at all times.
- All overhead utilities including power and communications will be placed underground to the West side of the HRSD main
- There are 2 waterlines on the east side of the bridge. One will remain in place; it is buried and will remain in the creek. The other will be relocated on the bridge.
- Utilities given authorization to begin undergrounding February 17, 2009
- Bryant Contracting receiving Notice to Proceed for July 6, 2009
- Anticipated final completion of August 30, 2010
Project Timeline: